Texas Rebuilders Weekly Report Dec 20, 2019

12/19/2019

This week we were able to get the laundry room sided, the roof finished, and we painted. We also got all finish work on the inside completed. The siding and trim got painted. The electrical work was completed. All the appliances were delivered and we were able to get them installed. Thursday afternoon we had fresh baked cookies, hot chocolate and coffee for the home owner, three of her children, and the case worker. We were able to give the home owner the Bible and keys to the house. She will be able to celebrate Christmas in her home. I got to cuddle with a seven week old baby, just an added benefit.

Barb and Jack Schmoll, Team Leaders