Oklahoma DR Weekly Report March 17th

3/17/2017
Elmore City Disaster Rebuild - March 11-16, 2017 We have continued to work on Mr. Steven’s house this week. Although just a week ago we put out a call for help and God helped to get Danny, Bob and Paige to respond and all arrived by Sunday evening.  The cold weather also arrived on Sunday evening as we had freezing weather greet us. This great team was able to get the rest of the drywall installed, then we taped and mudded. By mid-week we had skip textured all of the walls and ceilings. We had...

Volunteers doing Mighty Work in Oklahoma

3/4/2017
Click on the link below for the United Methodist Disaster Response of Oklahoma's update: http://eepurl.com/cD2OOf

Why we do what we do

3/4/2017
We have been working at Mr Steven's home for the last 2 weeks, the Armstrongs, Shumates and the Schmolls. Mr Stevens is 81, a retired Church of God pastor with bad eyesight, and has a hard time climbing stairs. He lives in a 2 story garage next to his house, that he has given to his children and grandchildren. He works for WALMART, Tuesday-Saturday to make ends meet. He is the SWEETEST man I have ever met. He is having a hard time with change and could not decide if he really wanted a new ...

Team Wimberley Weekly Report March 3rd

3/3/2017
Disaster Rebuilding in Wimberley Feb 27 – Mar 2 We had 5 RV units on the project this week and 9 people.  On Sunday we welcomed Don back to the team, Ken and Pat also joined the team. The new leaders Rob and Helen are here to take over the leadership for the last 4 weeks of this project. Cypress – With the floor tile finally arriving we were able to get it laid into the lower bathroom and finish the painting of the room. Lea Lane – Most of the team worked on this project this week. The back ...

Weekly Report - Wimberley Disaster Rebuild Feb 24th

2/24/2017
Disaster Rebuilding in Wimberley Feb 20 – 23 This week we had 5 RV units on site for our work. We said good bye to Herman and Levina Luymes, Bob and Onne Oelke, and Jeff Ausborn with a dinner at the Italian Garden restaurant. Our mornings were cool but warmed up quickly with daily highs in the mid to upper 80’s. We had a severe thunderstorm move through on Sunday evening into Monday morning with high winds and heavy rain. We did not work at Cypress Lane this week as we are waiting on tile for ...

Oklahoma Disaster Rebuilding Feb 17, 2017

2/19/2017
Work is in Maysville 14 miles from Elmore City.   Our team, Max and Anne Armstrong, Gwen and I worked the week finishing a home for the Williams. Their home had been under reconstruction since October. There was three feet of water/mud in the home requiring total tear down inside. We arrived in the end of the rebuild. Our task was to finish Installing baseboard, door molding, closet shelves, bathroom shelves. We finished painting walls, ceilings and molding. Finally cut and installed ceramic ...

Disaster Rebuilding in Wimberley Feb. 17th

2/17/2017
Disaster Rebuilding in Wimberley Feb 13 – 16 We had 7 units this week with 13 Nomads on the project. Cypress Lane – This week the team removed the water heater to complete the dry walling of the closet it was in. We also fixed the electrical and installed the pan drain for it. The ceiling repair including the installation of crown molding was completed and painted. The glass tile on the shower was installed and grouted and the backsplash in the kitchen completed. The wall outside the entry ...

Wimberley Week Ending Feb. 2nd

2/4/2017
Wimberley TX DR Project – Jan. 30 thru Feb. 2, 2017 10 Matador – Painted and installed 2 new doors for the bathrooms, installed vanity and top in main bath, painted new textured wall in main bath and installed water closet. In the kitchen dishwasher was installed, dented sink repaired and installed, tile backsplash installed and grouted, oak panels for backs of cabinets installed, stained and polyurethane applied. Light fixture in main bath installed, baseboard trim completed, final paint ...

Dakota Wesleyan Winter Issue-NOMADS

2/1/2017
Click on the link below to view the winter issue of the Dakota Wesleyan Today newsletter, featuring NOMADS on pages 15-17.   https://www.dwu.edu/alumni-visitors/wesleyan-today-alumni-magazine

Weekly Report from Team Wimberley

1/28/2017
Wimberley TX Disaster Rebuilding Project – Jan. 23 – 26 Matador St. – In the kitchen the work on the counter tops continued with the Formica cut and glued to the main "L" shaped top along with the island top. The sink hole has been cut out and it was decided to do a 4” high backsplash using ceramic tile. The back entry door was finished as it needed the door stop extended and weather seal installed. The master bedroom – it was decided to not install a sliding (barn type) door for the master ...